The scope of work of this EPC Project includes Engineering, Supply, Installation and Testing & Commissioning of two132/13.8 KV Substations as follows:

  • 3 Bays 132 GIS Ext.
  • 30 Breakers 13.8 KV
  • 33 KV Switchgears
  • 3 X 40 + 2 X 40 MVA Transformers
  • Protection & Control System
  • SCADA System
  • Sequences of Event Recorders
  • Transient Fault Recorders
  • Electromechanical Work
  • HVAC Work
  • Civil Work / Buildings :
    • GIS / Switchgear Building} 1,000 m2
    • Medium Voltage/Control Building}
Sakaka & Al-Jouf, Saudi Arabia
56 Millions
SEC-EOA
Oct 3, 2004 to Oct 31, 2007
POWER GENERATION & TRANSMISSION
AJEC