BEMCO to carry out the replacement of existing Filter Houses of the Turbine and Generator Sections with associated explosion proof equipment and connections at the Jeddah Oil Refinery.
Scope of Work
- The works also include the removal of the old filters and the construction of concrete foundations for the new Turbine Filter, Generator Filter and air compressor.
- The new filters have to be installed, tested and commissioned during a 15-day-shut-down period of the plant.
- The work is being executed in accordance with the strict safety regulations and highest standards of SAMAREC.
Jeddah, Saudi Arabia
2 Millions
SAMAREC JORC
Sept. 1992 To Aug. 1993
COMPLETED INDUSTRIAL