Project Description
Two Grades of Gasoline & Additional Capacity Requirements South West Bulk Plants in Abha, Jizan, and Najran Contract No. 6600012795
Scope of Work
Contractor scope of work shall include but not be limited to procurement, fabrication, forwarding and shipping, insurance, inland transportation, off-loading materials, storage and handling, construction, including all construction materials, tools & equipment, special tools (if any), local purchasing and manpower, quality control, inspection and testing, pre- commissioning, commissioning and performance testing assistance of the facilities in the Three (3) Bulk Plants. These facilities comprising mainly of the following, loading pumps, fire fighting system, oily drains, overhead lines, MV system, communications, SCADA system, instrumentation, buildings, roads & civil works. Aramco supplied equipment are TMS, loading modules, pumps & MV equipment).