Project Details
Location
Value in SR
Client
Period
Type
Consultant
Project Description
The project scope is a turn key job including detailed engineering, supply, installation, testing, commissioning and one year warranty of chiller plant to produce 30,000 tons of refrigeration.
Scope of Work
- Ten (10) chiller units with 2,500 tons nominal each.
- Thermal energy storage (TES) tank providing the remainder of the capacity.
- Eight (8) cells cooling towers.
- Chilled water pumps and condenser water pumps.
- Instrumentation and controls.
- Electric power supply.
- Equipment variable frequency drives.
- Building construction with approximate dimension of 61 meters by 56 meters inclusive of basement, ground floor, mezzanine floor and roof.
- Building services including air conditioning, plumbing, electrical and fire fighting works.
- Site developing, roads, walkways, Employees Parking Spaces with canopy, Security Fence and gates etc.
- TES Chilled Water Storage Tank, Water Storage Tanks.
Doha, Qatar
138 Millions
Qatar Cool
Feb 20, 2006 to Jul 20, 2007
COMPLETED INDUSTRIAL
Parsons International Ltd.