Arabian Bemco Contracting Co. submitted technical proposal for a 500 MW Steam Power Plant Unit No. 5 & 6 to Power and
Water Utility Company for Jubail & Yanbu (Marafiq).
Marafiq is intending to award the contract on EPC Turnkey Basis for the Construction of STG Units 5&6 at Marafiq Yanbu Plant by adding two (2) Steam Turbine Generator Units 250 MW each, two (2) Boilers, two (2) FGDs, along with necessary Balance of Plant including ESP, Chimney, DCS, Mechanical, Electrical Integration and Interfacing with the existing units and related civil works.
Technical Proposal was submitted on April 6, 2009.