Scope of works

is the Design, Engineering, Material Procurement, Quality Management, Factory Inspection, Testing & Commissioning and all associated works and services until final handing over of heavy duty industrial package type, simple cycle combustion gas turbine generator plant. Standard proven design of gas

turbine generators having a net rating of 60-80+10% MW base load at 50oC ambient temperature and reference site ambient conditions totaling approximately 1200 MW (60Hz units), shall be proposed. Crude oil is the main fuel with Natural gas as a back-up fuel and distillate for shut down and start-up. The proposal shall also include provisions for future conversion to Combined Cycle and Turbine Inlet Air Cooling System (TIAC). The scope shall include but not limited to the following:
Supply and installation of electrical BOP systems:

  • 132/380 KV 500 MVA transformers (4 Nos)
  • 4 x 110 MVA 13.8/132 KV
  • 8 x 220 MVA 13.8-13.8/132 KV
  • 380 KV GIB connecting the transformers to the GIS substation.
  • Auxiliary & station transformers.
  • MV switchgear.
  • LV switchgear.
  • MV, LV & Control Cables.
  • Isolated phase and non-segregated Busducts.
  • Communication & Security Systems.
  • Grounding Systems.
  • Lighting Systems.

Supply and installation of mechanical BOP Systems :

  • Fire Fighting Systems.
  • Ventilation Systems.
  • Water Systems.
  • Drainage Systems.
  • Black Start Generators.
  • Instrument and Service Compressed Air Systems.
  • 70 KM fuel pipeline.
  • 2 Nos. water deep wells.
  • Laboratory & workshop equipment.
  • Mobile Equipment.

U & O Plant Buildings.

  • 1. Steel Frame and Concrete Structure Over 100,000.-m2 of Buildings:
  • Turbine Building (A & B). 29,582 m2
  • Turbine Bldg. A & B Administrative Annex (4 Nos). 1,288 m2
  • Warehouse Building +mezzanine 3,075 m2
  • Workshop + mezzanine 3,002 m2
  • Miscellaneous Storage.
  • 1,024 m2
  • Fire & Foam PH Station.
  • 432 m2
  • Inflammable Products Storage 1,024 m2
  • Fuel Additives Storage Bldg. 1,024 m2
  • Laboratory Buildings (4 Nos.). 800 m2
  • Main Control Building.
  • 1,345 m2
  • Fire Station Building. 988 m2
  • Security Building. 576 m2
  • Administration Building. 2,630 m2
  • Plant Mosque. 370 m2
  • Nitrogen Building. 129 m2
  • Hydrogen Building. 259 v
  • 2. Housing Community:
  • Family Accommodation Type A, B & C. 29,778 m2
  • Housing Mosque. 829 m2
  • Bachelor Accommodation 9,318 m2
  • Shopping Center. 1,660 m2
  • National Guard Building.
  • 720 m2

U & O Earth works, Road, and Infrastructure

  • Earth works: over 2.-Million cum.
  • Road: around 25.-Km.
  • Storm Water Channel: 5.-Km.
  • Water Treatment and Pump House. 3,930 m2
  • Sewage Treatment
  • Metering Shelters.
  • Well water Transformer
  • Diesel / Oil Transfer Pumping Station. 1,376 m2
  • Parking lot
Riyadh, Saudi Arabia
1730 Millions
SCECO - C
June 1995 To Jan. 2001
POWER GENERATION & TRANSMISSION
EWI